# A transmission line or renewable project wants my land

The rebuild of the electricity network is reaching private land across New South Wales: new high-voltage transmission lines such as [HumeLink](https://stonepillar.com.au/resources/nsw-project-watch/#project-humelink) and [EnergyConnect](https://stonepillar.com.au/resources/nsw-project-watch/energyconnect/) , renewable energy zone infrastructure, and the wind, solar and storage projects that connect to them. Some of this arrives as a compulsory easement backed by statute; some arrives as a commercial offer. The two need very different responses.

- Jurisdiction

  New South Wales

- Page type

  Issue overview

On this page

- [This page may be relevant if:](https://stonepillar.com.au/issues/transmission-easements/#for-you-if)
- [What this usually means](https://stonepillar.com.au/issues/transmission-easements/#what-it-means)
- [What commonly matters](https://stonepillar.com.au/issues/transmission-easements/#what-matters)
- [How we help](https://stonepillar.com.au/issues/transmission-easements/#how-we-help)
- [Frequently asked questions](https://stonepillar.com.au/issues/transmission-easements/#questions)

If you have received a decision or notice, a strict review or appeal period may already be running. Confirm it promptly and do not rely on an online enquiry.

## This page may be relevant if:

- A transmission project has contacted you about access or an easement
- You have been offered an option deed, access licence or hosting agreement
- A renewable energy zone or connection project affects your district
- You have received an acquisition notice or compensation offer for an easement

## What this usually means

- Authorised network operators can compulsorily acquire transmission easements, with compensation assessed under the _Land Acquisition (Just Terms Compensation) Act 1991_, including the effect on the rest of the holding. A network operator must obtain the Minister's approval before giving a proposed acquisition notice.
- Before acquisition, landholders are typically asked to sign access deeds and option agreements for surveys and route refinement; their terms, and the conduct standards they set, are negotiable.
- Eligible landholders hosting new major transmission may also receive strategic benefit payments, calculated per kilometre hosted and paid over an extended period, in addition to compensation for the easement itself.
- Renewable energy projects such as wind and solar generally proceed by negotiated agreement. The lease or licence provides important contractual protection and should be considered alongside the project's approval conditions and any applicable statutory rights.

## What commonly matters

1. ### Compulsion or agreement

   Whether the project can ultimately compel an easement changes the negotiation; knowing which footing you are on is the starting point.

2. ### The whole-of-farm impact

   Compensation should reflect the easement's effect on the entire operation, including severance, access, irrigation and future development, not just the strip taken.

3. ### Terms beyond money

   Construction conduct, biosecurity, access notice, rehabilitation and dispute terms determine what living with the project is actually like.

4. ### Payments and structure

   Compensation, strategic benefit payments and hosting revenue have different characters. Their tax treatment is a matter for a tax adviser, and is best checked before the structure is agreed; we do not provide tax advice.

## How we help

- Review and negotiate access deeds, options and hosting agreements
- Act through the easement acquisition and compensation process
- Prepare valuation and whole-of-farm evidence with your experts
- Negotiate conduct, rehabilitation and dispute terms that protect the land

## Project Watch examples

- [NSW Project Watch — Project EnergyConnect](https://stonepillar.com.au/resources/nsw-project-watch/energyconnect/)
- [NSW Project Watch — Central-West Orana Renewable Energy Zone (transmission)](https://stonepillar.com.au/resources/nsw-project-watch/central-west-orana-rez/)
- [NSW Project Watch — Hunter Transmission Project](https://stonepillar.com.au/resources/nsw-project-watch/hunter-transmission-project/)
- [NSW Project Watch — HumeLink](https://stonepillar.com.au/resources/nsw-project-watch/humelink/)
- [NSW Project Watch — VNI West (NSW section) and South West REZ network upgrade](https://stonepillar.com.au/resources/nsw-project-watch/vni-west-nsw/)

## Related reading

- [Land access and easements — NSW transmission easements: refusing an agreement and protecting landowner rights — NSW transmission easements: refusing an agreement, challenging acquisition, protecting retained land and separating compensation from benefit payments.](https://stonepillar.com.au/insights/nsw-transmission-easements-landowner-rights/)
- [Compulsory acquisition — Choosing a lawyer for a compulsory acquisition claim in NSW — How a NSW landowner chooses a compulsory acquisition lawyer: the work at each stage, who the lawyer acts for, who runs the claim, costs and the Court.](https://stonepillar.com.au/insights/choosing-a-compulsory-acquisition-lawyer-nsw/)
- [Compulsory acquisition — Disadvantage resulting from relocation in NSW acquisitions — When disadvantage resulting from relocation (formerly solatium) is payable in a NSW acquisition, how the indexed cap works and the evidence for a claim.](https://stonepillar.com.au/insights/disadvantage-resulting-from-relocation-nsw/)

This page is general information only and is not legal advice. It may not be current, and how the law applies depends on the specific facts. For advice on your situation, contact Stone & Pillar Legal.

## A transmission proposal may affect your property

Tell us the project, the stage reached and any easement or access proposal received.

The preliminary call covers

- What has happened and the decision you need to make
- The authority or other party involved, so we can check for conflicts
- Any date stated in the documents you have received
- Whether the firm can assist, and what a scoped first step would involve

Tell us which document you received, who issued it and any date it states. Keep it to hand for the call.

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=property&issue=transmission-easements#schedule)

[Request a call back](https://stonepillar.com.au/contact/?matter=property&issue=transmission-easements#enquiry)

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

Prefer to talk? [(02) 8014 5817 ](tel:+61280145817)· [Email](mailto:enquiries@stonepillar.com.au)

Your enquiry will be reviewed by Michael Themis , Principal Solicitor of Stone & Pillar Legal.

What to bring

- Any deed, option, licence or agreement offered
- Project correspondence, maps or alignment plans
- Details of the property, its operation and any plans for it
- Any compensation offer or valuation received

[Related practice area Land access, easements, roads and infrastructure impacts](https://stonepillar.com.au/services/land-access-easements/)

Tools and resources

- [NSW Project Watch: check a public project against your land](https://stonepillar.com.au/resources/nsw-project-watch/)

## Frequently asked questions

General information only, not legal advice. The position depends on your circumstances.

Can I refuse a transmission easement on my land?

You can decline to reach agreement, but where the project has the benefit of a statutory acquisition power the easement can generally be acquired compulsorily, with compensation assessed under the _Land Acquisition (Just Terms Compensation) Act 1991_ (NSW). Negotiation still matters: route detail, construction conduct, rehabilitation, access terms and compensation can all be negotiated, and an offer can be tested with property-specific and valuation evidence before it is accepted. Knowing whether the project can ultimately compel the easement is the starting point for the whole negotiation.

What are strategic benefit payments for hosting transmission?

Eligible landholders hosting specified new high-voltage transmission infrastructure may receive annual indexed strategic benefit payments during the project's 20-year payment period. Eligibility and the remaining payment period depend on the project, holding and relevant dates; a new recipient should not assume they will receive 20 payments. These payments sit alongside compensation for the easement and must be disregarded when assessing compensation under Part 3 of the _Land Acquisition (Just Terms Compensation) Act 1991_. Confirm eligibility, calculation and administration for the particular line and landholding.

Should I sign the access deed or option I have been offered?

Not before it is reviewed. Access deeds and option agreements set the terms for surveys, investigations and sometimes years of dealings that follow, including notice periods, biosecurity protocols, compensation for damage, and how disputes are handled. They are drafted by the proponent and are negotiable. Whether the proponent will contribute to the cost of your advice, and on what terms, should be confirmed in writing before the advice is obtained. What is agreed at this early stage tends to set the tone, and the baseline, for the easement negotiation that follows, so it rewards the same care as the final documents.

## Related situations

- [Compulsory acquisition — I received a Proposed Acquisition Notice — A Proposed Acquisition Notice starts a defined pre-acquisition timetable. Understand what it means, the compensation claim period and the first steps that protect your position.](https://stonepillar.com.au/issues/proposed-acquisition-notice/)
- [Compulsory acquisition — My land is being acquired — Advice on proposed acquisition notices, compensation claims, valuation issues and disturbance losses.](https://stonepillar.com.au/issues/land-acquisition/)
- [Water & land — A mining, gas or water project affects my land — Advice on exploration and mining access, coal seam gas, aquifer and water-licensing impacts, and compensation where resource projects affect your land.](https://stonepillar.com.au/issues/resource-impact/)
- [Water & land — I have an easement, covenant or access dispute — Easement scope and obstruction disputes, court-imposed easements under section 88K, covenants and neighbouring land access.](https://stonepillar.com.au/issues/easement-disputes/)

[All situations](https://stonepillar.com.au/issues/)

Where to start

## Discuss an energy project affecting your land

Start with the project, the proposed use of your land and your priorities. On a short preliminary call we can tell you whether we can assist and what the first step would be.

[Request a call back](https://stonepillar.com.au/contact/?matter=property&issue=transmission-easements#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=property&issue=transmission-easements#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.