# Elizabeth Drive Upgrade (Western Sydney)

Road · Greater Sydney · Transport for NSW

Documented stage: **Procurement / delivery**

Profile publication reviewed 20 November 2026. Individual source-check dates appear below. Inclusion does not establish that any particular property will be acquired or affected.

On this page

- [Project overview](https://stonepillar.com.au/resources/nsw-project-watch/elizabeth-drive-upgrade/#overview)
- [Possible land impacts](https://stonepillar.com.au/resources/nsw-project-watch/elizabeth-drive-upgrade/#land-impacts)
- [Documents to gather](https://stonepillar.com.au/resources/nsw-project-watch/elizabeth-drive-upgrade/#documents)
- [Council areas](https://stonepillar.com.au/resources/nsw-project-watch/elizabeth-drive-upgrade/#location)
- [Official sources](https://stonepillar.com.au/resources/nsw-project-watch/elizabeth-drive-upgrade/#sources)

## Project overview

Transport for NSW is widening Elizabeth Drive in Western Sydney to a four-lane divided road between Badgerys Creek Road and Devonshire Road. Early works are under way and the main works contract has been awarded.

- [Transport for NSW, Elizabeth Drive Upgrade](https://www.transport.nsw.gov.au/projects/current-projects/elizabeth-drive-upgrade)

### Early works and main works

Decmil holds the early works contract. Early work along Elizabeth Drive and Mamre Road was scheduled from 14 October 2026, and Transport for NSW says early works are under way. The Gamuda-BMD Joint Venture holds the main works contract between Badgerys Creek Road and Devonshire Road, with design development under way. The NSW Government's announcement of 21 September 2026 lists Elizabeth Drive at $1 billion.

- [Transport for NSW, Elizabeth Drive Upgrade](https://www.transport.nsw.gov.au/projects/current-projects/elizabeth-drive-upgrade)
- [Transport for NSW, Elizabeth Drive and Mamre Road Stage 2 early work notification (September 2026)](https://www.transport.nsw.gov.au/system/files/media/documents/2026/elizabeth-dr-upgrade-project-notification-september-2026.pdf)
- [NSW Government, Western Sydney road contracts announcement (21 September 2026)](https://www.nsw.gov.au/ministerial-releases/mammoth-investment-nearly-3-billion-worth-of-road-projects-on-way-for-western-sydney)

### What the upgrade includes

The design replaces the bridges over Badgerys Creek and South Creek with twin bridges, makes Lawson Road and Clifton Road left in and left out, adds traffic lights at Martin Road, Western Road and Devonshire Road, and provides new paths for pedestrians and cyclists. Transport for NSW says the wider corridor leaves space for additional lanes in future, if required.

- [Transport for NSW, Elizabeth Drive Upgrade](https://www.transport.nsw.gov.au/projects/current-projects/elizabeth-drive-upgrade)

### Environmental assessment

Transport for NSW published reviews of environmental factors for the east and west sections in September 2023, and submissions reports in October 2024. An addendum for the east section, covering changed road alignments and intersections, bridge arrangements, and flooding and drainage infrastructure, was determined on 25 May 2026.

- [Transport for NSW, Elizabeth Drive Upgrade](https://www.transport.nsw.gov.au/projects/current-projects/elizabeth-drive-upgrade)
- [Transport for NSW, Elizabeth Drive East Upgrade addendum decision statement (25 May 2026)](https://www.transport.nsw.gov.au/system/files/media/documents/2026/Decision%20Statement.pdf)

## What this could mean for a property

Widening and upgrading an existing road corridor can require strips of adjoining land (partial acquisition), and sometimes whole-property acquisition. This design also changes access: Lawson Road and Clifton Road become left in and left out, and the early works include a new service road at Kemps Creek. A project being planned near you does not mean your property will be acquired.

### Key things to watch

- The proposed corridor and widening extent
- Whether your land or access is affected
- Any survey, valuation or acquisition correspondence
- Interaction with Aerotropolis precinct planning

### Possible land impacts

- Partial acquisition of adjoining land for widening, and whole acquisition in places
- Severance and access effects for retained land
- Changed property and driveway access
- Construction and precinct-planning effects on value

## Possible impact types

- Partial acquisition
- Whole-property acquisition
- Severance / retained land
- Access change
- Business disturbance
- Noise / vibration / amenity
- Planning / corridor constraint

## Documents worth gathering

- Any letter or notice from the project
- Your title search and deposited plan
- Valuation, rating or appraisal material
- Business records, if a business is affected

## Location and relevant interests

**Council areas:** Penrith, Liverpool, Fairfield.

**Often relevant to:** Owners and occupiers along the corridor; Businesses fronting or near the road; Owners in the surrounding growth precincts.

## Related land guidance

- [Partial acquisitions and retained land](https://stonepillar.com.au/issues/partial-acquisitions/)
- [My land is being acquired](https://stonepillar.com.au/issues/land-acquisition/)
- [Affected by a project](https://stonepillar.com.au/issues/affected-by-project/)
- [Compulsory acquisition](https://stonepillar.com.au/services/compulsory-acquisition/)

## Official sources

- [Transport for NSW, Elizabeth Drive Upgrade](https://www.transport.nsw.gov.au/projects/current-projects/elizabeth-drive-upgrade)

  Source checked 20 November 2026.

- [Transport for NSW, Elizabeth Drive and Mamre Road Stage 2 early work notification (September 2026)](https://www.transport.nsw.gov.au/system/files/media/documents/2026/elizabeth-dr-upgrade-project-notification-september-2026.pdf)

  Source checked 20 November 2026.

- [Transport for NSW, Elizabeth Drive East Upgrade addendum decision statement (25 May 2026)](https://www.transport.nsw.gov.au/system/files/media/documents/2026/Decision%20Statement.pdf)

  Source checked 20 November 2026.

- [NSW Government, Western Sydney road contracts announcement (21 September 2026)](https://www.nsw.gov.au/ministerial-releases/mammoth-investment-nearly-3-billion-worth-of-road-projects-on-way-for-western-sydney)

  Source checked 20 November 2026.

- [Infrastructure NSW, Major Projects Pipeline (Construction Procurement)](https://www.infrastructure.nsw.gov.au/industry/construction-industry/pipeline-of-projects/)

  Source checked 20 November 2026. Row read on 20 November 2026 from the pipeline page, last updated 28 September 2026: Stage 1, Devonshire Road to Badgerys Creek, in construction procurement.

Project record checked 19 October 2026

Project information is indicative. It does not establish that a particular property is affected.

[Discuss this project : Elizabeth Drive Upgrade (Western Sydney)](https://stonepillar.com.au/contact/?matter=acquisition&project=elizabeth-drive-upgrade#enquiry) [Watch this project : Elizabeth Drive Upgrade (Western Sydney)](https://stonepillar.com.au/resources/nsw-project-watch/?watch=elizabeth-drive-upgrade#watch)

About the dates: the publication review records when this profile was approved for publication. Each official source has its own check date. The project record date refers to the catalogue entry. These dates do not establish that later project changes have been checked.

To cite this page: Stone & Pillar Legal, “Elizabeth Drive Upgrade (Western Sydney)”, NSW Project Watch, profile reviewed 20 November 2026, https\://stonepillar.com.au/resources/nsw-project-watch/elizabeth-drive-upgrade/

This page provides general information only. Project details may change and should be checked against official sources. The inclusion of a project on this page does not mean that any particular property will be acquired or affected. This page is not legal advice. Submitting an enquiry does not create a solicitor–client relationship, and any engagement is subject to conflict checks and written terms of engagement.

## Related project profiles

- [Sydney Metro, Western Sydney Airport line](https://stonepillar.com.au/resources/nsw-project-watch/sydney-metro-western-sydney-airport/)
- [Western Sydney Aerotropolis, land reserved for acquisition](https://stonepillar.com.au/resources/nsw-project-watch/western-sydney-aerotropolis-land-reservation/)

[Find this project on the Project Watch hub](https://stonepillar.com.au/resources/nsw-project-watch/#project-elizabeth-drive-upgrade)

Where to start

## Discuss your project or land concern

Tell us what has happened and what decision you need to make. The preliminary call is to discuss whether Stone & Pillar can assist and the next step. If we can assist, scope and fees are agreed before substantive legal work begins.

[Request a call back](https://stonepillar.com.au/contact/?matter=acquisition#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=acquisition&project=elizabeth-drive-upgrade#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.