NSW Project Watch

# Project EnergyConnect

Transmission and energy · Riverina and Southern NSW · Transgrid

Documented stage: **Construction**

Profile publication reviewed 27 October 2026. Individual source-check dates appear below. Inclusion does not establish that any particular property will be acquired or affected.

On this page

- [Project overview](https://stonepillar.com.au/resources/nsw-project-watch/energyconnect/#overview)
- [Possible land impacts](https://stonepillar.com.au/resources/nsw-project-watch/energyconnect/#land-impacts)
- [Documents to gather](https://stonepillar.com.au/resources/nsw-project-watch/energyconnect/#documents)
- [Council areas](https://stonepillar.com.au/resources/nsw-project-watch/energyconnect/#location)
- [Official sources](https://stonepillar.com.au/resources/nsw-project-watch/energyconnect/#sources)

## Project overview

EnergyConnect is an electricity interconnector of about 900 kilometres linking the NSW, South Australian and Victorian grids. Transgrid reports that construction and initial energisation are complete, with commissioning and testing continuing.

- [Transgrid, EnergyConnect](https://www.transgrid.com.au/projects-innovation/energyconnect/)

### The NSW route

The interconnector includes 330 kV and 500 kV transmission lines. In NSW it runs from the South Australian border to Buronga, then to a new substation at Dinawan near Bundure, and on to Wagga Wagga.

- [Transgrid, EnergyConnect](https://www.transgrid.com.au/projects-innovation/energyconnect/)

### Rehabilitation and commissioning

Transgrid reports that rehabilitation of the project corridor, commissioning and testing are in progress. Integration into the National Electricity Market is expected by the end of 2026.

- [Transgrid, EnergyConnect](https://www.transgrid.com.au/projects-innovation/energyconnect/)

## What this could mean for a property

The line is built, but the property questions it raised can outlast construction. EnergyConnect was delivered through easements over private land, and Transgrid states that compensation is paid under the Land Acquisition (Just Terms Compensation) Act 1991. Transgrid also states that the NSW Government's Strategic Benefit Payments, a set rate per kilometre of line hosted paid annually over 20 years, apply to landowners hosting EnergyConnect, in addition to that compensation. Owners whose compensation is not yet settled, or who are unsure what they are entitled to, may want to check where their claim stands.

### Key things to watch

- Whether your compensation claim has been made, determined or settled
- Strategic Benefit Payments and how they are paid
- The easement terms, including access and land-use restrictions
- Rehabilitation of the corridor, including land and fences, while it is under way

### Possible land impacts

- Transmission easements over private and rural land
- Restrictions on land use, building and farming within the easement
- Continuing access for operation and maintenance

## Possible impact types

- Easement
- Planning / corridor constraint

## Documents worth gathering

- The easement instrument and any agreement you signed
- Your title search and deposited plan
- Correspondence about compensation and Strategic Benefit Payments
- Farm and business records, if relevant

## Location and relevant interests

**Council areas:** Wentworth, Murrumbidgee, Wagga Wagga.

**Often relevant to:** Rural and agricultural landholders hosting the easement; Owners adjoining the line; Lessees and farm businesses.

## Related land guidance

- [Transmission or renewables](https://stonepillar.com.au/issues/transmission-easements/)
- [Compulsory acquisition](https://stonepillar.com.au/services/compulsory-acquisition/)
- [Acquisition notices and process](https://stonepillar.com.au/issues/land-acquisition/)
- [Affected by a project](https://stonepillar.com.au/issues/affected-by-project/)

## Official sources

- [Transgrid, EnergyConnect](https://www.transgrid.com.au/projects-innovation/energyconnect/)

  Source checked 27 October 2026.

- [Transgrid, EnergyConnect: landowner and community engagement](https://www.transgrid.com.au/projects-innovation/energyconnect/landowner-and-community-engagement/)

  Source checked 27 October 2026.

Project record checked 19 October 2026

Project information is indicative. It does not establish that a particular property is affected.

[Discuss this project : Project EnergyConnect](https://stonepillar.com.au/contact/?matter=acquisition&project=energyconnect#enquiry) [Watch this project : Project EnergyConnect](https://stonepillar.com.au/resources/nsw-project-watch/?watch=energyconnect#watch)

About the dates: the publication review records when this profile was approved for publication. Each official source has its own check date. The project record date refers to the catalogue entry. These dates do not establish that later project changes have been checked.

To cite this page: Stone & Pillar Legal, “Project EnergyConnect”, NSW Project Watch, profile reviewed 27 October 2026, https\://stonepillar.com.au/resources/nsw-project-watch/energyconnect/

This page provides general information only. Project details may change and should be checked against official sources. The inclusion of a project on this page does not mean that any particular property will be acquired or affected. This page is not legal advice. Submitting an enquiry does not create a solicitor–client relationship, and any engagement is subject to conflict checks and written terms of engagement.

## Related project profiles

- [Central-West Orana Renewable Energy Zone (transmission)](https://stonepillar.com.au/resources/nsw-project-watch/central-west-orana-rez/)
- [Hunter Transmission Project](https://stonepillar.com.au/resources/nsw-project-watch/hunter-transmission-project/)
- [VNI West (NSW section) and South West REZ network upgrade](https://stonepillar.com.au/resources/nsw-project-watch/vni-west-nsw/)

[Find this project on the Project Watch hub](https://stonepillar.com.au/resources/nsw-project-watch/#project-energyconnect)

Where to start

## Discuss your project or land concern

Tell us what has happened and what decision you need to make. The preliminary call is to discuss whether Stone & Pillar can assist and the next step. If we can assist, scope and fees are agreed before substantive legal work begins.

[Request a call back](https://stonepillar.com.au/contact/?matter=acquisition#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=acquisition&project=energyconnect#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.