# HumeLink

Transmission and energy · Riverina and Southern NSW · Transgrid

Documented stage: **Construction**

Profile publication reviewed 20 November 2026. Individual source-check dates appear below. Inclusion does not establish that any particular property will be acquired or affected.

On this page

- [Project overview](https://stonepillar.com.au/resources/nsw-project-watch/humelink/#overview)
- [Possible land impacts](https://stonepillar.com.au/resources/nsw-project-watch/humelink/#land-impacts)
- [Documents to gather](https://stonepillar.com.au/resources/nsw-project-watch/humelink/#documents)
- [Council areas](https://stonepillar.com.au/resources/nsw-project-watch/humelink/#location)
- [Official sources](https://stonepillar.com.au/resources/nsw-project-watch/humelink/#sources)

## Project overview

A 500 kV electricity transmission line connecting Wagga Wagga, Bannaby and Maragle in southern NSW, with about 365 kilometres of new transmission lines. Transgrid says main construction is in progress on the HumeLink East and HumeLink West sections, and lists the end of construction as proposed for 2027.

- [Transgrid, HumeLink](https://www.transgrid.com.au/projects-innovation/humelink/)

### Route and scope

Transgrid describes HumeLink as a new 500 kV transmission line connecting Wagga Wagga, Bannaby and Maragle, with about 365 kilometres of new transmission lines and new or upgraded infrastructure at four locations. It says the main construction works include new substations at Gugaa and Maragle and upgrades to the existing substations at Bannaby and Wagga Wagga.

- [Transgrid, HumeLink](https://www.transgrid.com.au/projects-innovation/humelink/)

### Approvals and construction

Transgrid's project timeline records planning approval from the State government in November 2024 and from the Commonwealth government in December 2024. It shows construction of the transmission lines and substations as in progress, and the end of construction as proposed for 2027.

- [Transgrid, HumeLink](https://www.transgrid.com.au/projects-innovation/humelink/)

### Land and easements

Transgrid's timeline records that HumeLink reached Considered Project status in mid 2025, and says that for a project to be classed that way the necessary land and easements have to be acquired. Neither Transgrid page says whether the easement over any particular property has been acquired. The landowner page carries questions and answers on compulsory acquisition. They say Transgrid's preference is a negotiated outcome with easement affected landowners, that compulsory acquisition may start if a compensation agreement cannot be reached, and that Transgrid has exceeded the six-month negotiation period for the landowners it is contacting about compulsory acquisition. One of those answers describes the project as not yet approved.

- [Transgrid, HumeLink](https://www.transgrid.com.au/projects-innovation/humelink/)
- [Transgrid, HumeLink: information for landowners](https://www.transgrid.com.au/projects-innovation/humelink/information-for-landowners/)

### Strategic Benefit Payments

EnergyCo lists HumeLink among the transmission projects declared eligible for the NSW Strategic Benefit Payments Scheme. It says eligible landholders receive the equivalent of $200,000 in 2022 dollars for each kilometre of eligible transmission infrastructure hosted on their property, paid in annual instalments over 20 years, in addition to compensation for the easement.

- [EnergyCo, Strategic Benefit Payments Scheme](https://www.energyco.nsw.gov.au/community/information-for-landholders/strategic-benefit-payment-scheme)

## What this could mean for a property

Transmission projects are usually delivered through easements over private land rather than full acquisition. Transgrid's landowner page says its preference is a negotiated outcome with easement affected landowners, that compulsory acquisition may start if a compensation agreement cannot be reached, and that it has exceeded the six-month negotiation period for the landowners it is contacting about compulsory acquisition. Transgrid's timeline records planning approvals in November and December 2024, but one answer on its landowner page describes the project as not yet approved, so those answers may not reflect the current position. Neither page says whether any notice is being issued now. A Proposed Acquisition Notice is followed by statutory steps with time limits, including for claiming compensation and for objecting to the amount offered. The firm's guidance on Proposed Acquisition Notices and on disputing compensation sets those out. The easement terms, access conditions, construction impacts and compensation (including any strategic benefit payments) are worth understanding before signing anything.

### Key things to watch

- The easement terms, width and exact location
- Compensation, and any strategic benefit payments
- Access, biosecurity and construction conditions
- What happens if an agreement is not reached
- Whether you have received, or been told to expect, a Proposed Acquisition Notice, and the dates on it

### Possible land impacts

- Transmission easements over private and rural land
- Survey, geotechnical and construction access
- Construction compounds, temporary occupation and access tracks
- Farming, biosecurity and land-use effects within and near the easement

## Possible impact types

- Easement
- Survey / investigation access
- Construction lease
- Temporary occupation
- Access change
- Business disturbance
- Severance / retained land
- Planning / corridor constraint

## Documents worth gathering

- Any easement, option or land-access agreement offered
- Your title search and deposited plan
- Farm and business records, if relevant
- Correspondence and maps from the project

## Location and relevant interests

**Council areas:** Wagga Wagga, Snowy Valleys, Cootamundra-Gundagai Regional, Hilltops, Yass Valley, Upper Lachlan Shire, Goulburn Mulwaree.

**Often relevant to:** Rural and agricultural landholders; Owners hosting or adjoining the easement; Lessees and farm businesses.

## Related land guidance

- [Transmission or renewables](https://stonepillar.com.au/issues/transmission-easements/)
- [I received a PAN](https://stonepillar.com.au/issues/proposed-acquisition-notice/)
- [Compensation objections](https://stonepillar.com.au/issues/compensation-objections/)
- [Compulsory acquisition](https://stonepillar.com.au/services/compulsory-acquisition/)
- [Acquisition notices and process](https://stonepillar.com.au/issues/land-acquisition/)
- [Affected by a project](https://stonepillar.com.au/issues/affected-by-project/)

## Official sources

- [Transgrid, HumeLink](https://www.transgrid.com.au/projects-innovation/humelink/)

  Source checked 20 November 2026.

- [Transgrid, HumeLink: information for landowners](https://www.transgrid.com.au/projects-innovation/humelink/information-for-landowners/)

  Source checked 20 November 2026. Read on 20 November 2026. One of the page's answers on compulsory acquisition describes the project as not yet approved.

- [EnergyCo, Strategic Benefit Payments Scheme](https://www.energyco.nsw.gov.au/community/information-for-landholders/strategic-benefit-payment-scheme)

  Source checked 20 November 2026.

Project record checked 19 October 2026

Project information is indicative. It does not establish that a particular property is affected.

[Discuss this project : HumeLink](https://stonepillar.com.au/contact/?matter=acquisition&project=humelink#enquiry) [Watch this project : HumeLink](https://stonepillar.com.au/resources/nsw-project-watch/?watch=humelink#watch)

About the dates: the publication review records when this profile was approved for publication. Each official source has its own check date. The project record date refers to the catalogue entry. These dates do not establish that later project changes have been checked.

To cite this page: Stone & Pillar Legal, “HumeLink”, NSW Project Watch, profile reviewed 20 November 2026, https\://stonepillar.com.au/resources/nsw-project-watch/humelink/

This page provides general information only. Project details may change and should be checked against official sources. The inclusion of a project on this page does not mean that any particular property will be acquired or affected. This page is not legal advice. Submitting an enquiry does not create a solicitor–client relationship, and any engagement is subject to conflict checks and written terms of engagement.

## Related project profiles

- [VNI West (NSW section) and South West REZ network upgrade](https://stonepillar.com.au/resources/nsw-project-watch/vni-west-nsw/)

[Find this project on the Project Watch hub](https://stonepillar.com.au/resources/nsw-project-watch/#project-humelink)

Where to start

## Discuss your project or land concern

Tell us what has happened and what decision you need to make. The preliminary call is to discuss whether Stone & Pillar can assist and the next step. If we can assist, scope and fees are agreed before substantive legal work begins.

[Request a call back](https://stonepillar.com.au/contact/?matter=acquisition#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=acquisition&project=humelink#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.