# Hunter Transmission Project

Transmission and energy · Hunter · EnergyCo NSW

Documented stage: **Procurement / delivery**

Profile publication reviewed 27 October 2026. Individual source-check dates appear below. Inclusion does not establish that any particular property will be acquired or affected.

On this page

- [Project overview](https://stonepillar.com.au/resources/nsw-project-watch/hunter-transmission-project/#overview)
- [Possible land impacts](https://stonepillar.com.au/resources/nsw-project-watch/hunter-transmission-project/#land-impacts)
- [Documents to gather](https://stonepillar.com.au/resources/nsw-project-watch/hunter-transmission-project/#documents)
- [Council areas](https://stonepillar.com.au/resources/nsw-project-watch/hunter-transmission-project/#location)
- [Official sources](https://stonepillar.com.au/resources/nsw-project-watch/hunter-transmission-project/#sources)

## Project overview

The Hunter Transmission Project is a new overhead 500 kV transmission line of about 110 kilometres between Bayswater in the Upper Hunter and Olney in the Lower Hunter. The project has conditional approvals and is in procurement, with construction expected in 2027.

- [EnergyCo, Hunter Transmission Project](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project)
- [EnergyCo, Industry opportunities for the Hunter Transmission Project](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project/industry-opportunities)
- [Commonwealth approval decision, Hunter Transmission Project (EPBC 2024/09874), 9 September 2026](https://epbcpublicportal.environment.gov.au/_entity/sharepointdocumentlocation/80d75b35-2909-f011-bae3-00224811099e/2ab10dab-d681-4911-b881-cc99413f07b6?file=2024-09874-Approval-Decision.pdf)

### Infrastructure and approvals

The project includes new switching stations and upgrades to the Bayswater and Eraring substations. The NSW Government granted planning approval on 27 July 2026. Commonwealth approval was granted on 9 September 2026, subject to conditions, under EPBC 2024/09874.

- [EnergyCo, What we are building for the Hunter Transmission Project](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project/transmission-infrastructure)
- [NSW Planning Portal, Hunter Transmission Project approval (SSI-70610456)](https://www.planningportal.nsw.gov.au/major-projects/projects/hunter-transmission-project)
- [Commonwealth approval decision, Hunter Transmission Project (EPBC 2024/09874), 9 September 2026](https://epbcpublicportal.environment.gov.au/_entity/sharepointdocumentlocation/80d75b35-2909-f011-bae3-00224811099e/2ab10dab-d681-4911-b881-cc99413f07b6?file=2024-09874-Approval-Decision.pdf)

### Procurement and expected construction

Transgrid is the preferred network operator. Tenders for the two main design and construction packages are under way, and EnergyCo expects construction to start in 2027.

- [EnergyCo, Industry opportunities for the Hunter Transmission Project](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project/industry-opportunities)

### Easement acquisition and widths

EnergyCo says it has begun the formal easement acquisition process under the Land Acquisition (Just Terms Compensation) Act 1991 and that negotiations with affected landholders are ongoing. It describes construction within a temporary easement of about 140 metres, with a permanent easement of around 70 metres.

- [EnergyCo, Hunter Transmission Project landholder information](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project/landholder-information)

### Gazetted construction leases and easements

On 7 August 2026 EnergyCo gazetted compulsory acquisitions of construction leases for road upgrades whose lease terms name the Hunter Transmission Project, in NSW Government Gazette No 317. EnergyCo also gazetted compulsory acquisitions of 140 metre construction and access easements on 31 July and 18 September 2026, in Nos 305 and 381. Those two notices do not name a project.

- [NSW Government Gazette No 317 (7 August 2026), EnergyCo notice of compulsory acquisition naming the Hunter Transmission Project](https://gazette.nsw.gov.au/gazette/2026/8/2026-8_317-gazette.pdf)
- [NSW Government Gazette No 305 (31 July 2026), EnergyCo notice of compulsory acquisition (project not named)](https://gazette.nsw.gov.au/gazette/2026/7/2026-7_305-gazette.pdf)
- [NSW Government Gazette No 381 (18 September 2026), EnergyCo notice of compulsory acquisition (project not named)](https://gazette.nsw.gov.au/gazette/2026/9/2026-9_381-gazette.pdf)

## What this could mean for a property

Transmission projects are usually delivered through easements over private land rather than full acquisition. With NSW planning approval granted on 27 July 2026 and Commonwealth approval granted on 9 September 2026, subject to conditions, EnergyCo has begun the formal easement acquisition process, has gazetted a compulsory acquisition of construction leases for the project, and says negotiations with affected landholders are ongoing, so compulsory acquisition is possible where agreement is not reached. A property being near the approved corridor does not mean it will be affected, but the easement terms, access conditions, construction impacts and compensation are worth understanding before agreeing to anything.

### Key things to watch

- Whether your land is within or near the approved corridor
- Any easement offer, negotiation or formal acquisition notice from EnergyCo
- The easement terms, width and compensation
- What happens if an agreement is not reached

### Possible land impacts

- Transmission easements over private and rural land along the corridor
- Survey, geotechnical and construction access
- Construction compounds, temporary occupation and access tracks
- Severance and land-use effects within and near the easement

## Possible impact types

- Easement
- Survey / investigation access
- Construction lease
- Temporary occupation
- Access change
- Severance / retained land
- Planning / corridor constraint

## Documents worth gathering

- Any easement, option or land-access agreement offered
- Your title search and deposited plan
- Farm and business records, if relevant
- Correspondence and maps from the project

## Location and relevant interests

**Council areas:** Muswellbrook, Singleton, Cessnock, Lake Macquarie, Central Coast.

**Often relevant to:** Rural and regional landholders along the corridor; Owners hosting or adjoining the easement; Lessees and farm businesses.

## Related land guidance

- [Transmission or renewables](https://stonepillar.com.au/issues/transmission-easements/)
- [Affected by a project](https://stonepillar.com.au/issues/affected-by-project/)
- [Compulsory acquisition](https://stonepillar.com.au/services/compulsory-acquisition/)
- [Land access and easements](https://stonepillar.com.au/services/land-access-easements/)

## Official sources

- [Commonwealth approval decision, Hunter Transmission Project (EPBC 2024/09874), 9 September 2026](https://epbcpublicportal.environment.gov.au/_entity/sharepointdocumentlocation/80d75b35-2909-f011-bae3-00224811099e/2ab10dab-d681-4911-b881-cc99413f07b6?file=2024-09874-Approval-Decision.pdf)

  Source checked 27 October 2026. Approval and conditions appear on page 1; the decision date appears on page 2. This is a previously omitted approval, not a new October decision.

- [EnergyCo, Hunter Transmission Project](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project)

  Source checked 27 October 2026.

- [EnergyCo, Hunter Transmission Project landholder information](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project/landholder-information)

  Source checked 27 October 2026.

- [NSW Planning Portal, Hunter Transmission Project approval (SSI-70610456)](https://www.planningportal.nsw.gov.au/major-projects/projects/hunter-transmission-project)

  Source checked 27 October 2026.

- [NSW Government, Hunter Transmission Project approved (29 July 2026)](https://www.nsw.gov.au/ministerial-releases/hunter-transmission-project-approved-powering-jobs-and-connecting-clean-affordable-energy-to-nsw-homes)

  Source checked 27 October 2026. Historical announcement dated 29 July 2026. Its construction forecast and pending Commonwealth approval description have been superseded by the later project sources.

- [NSW Government Gazette No 305 (31 July 2026), EnergyCo notice of compulsory acquisition (project not named)](https://gazette.nsw.gov.au/gazette/2026/7/2026-7_305-gazette.pdf)

  Source checked 27 October 2026. The relevant EnergyCo notice does not name a project. It does not establish attribution to the Hunter Transmission Project.

- [NSW Government Gazette No 317 (7 August 2026), EnergyCo notice of compulsory acquisition naming the Hunter Transmission Project](https://gazette.nsw.gov.au/gazette/2026/8/2026-8_317-gazette.pdf)

  Source checked 27 October 2026.

- [NSW Government Gazette No 381 (18 September 2026), EnergyCo notice of compulsory acquisition (project not named)](https://gazette.nsw.gov.au/gazette/2026/9/2026-9_381-gazette.pdf)

  Source checked 27 October 2026. The relevant EnergyCo notice does not name a project. It does not establish attribution to the Hunter Transmission Project.

- [Infrastructure NSW, Major Projects Pipeline (earlier catalogue reference)](https://www.infrastructure.nsw.gov.au/industry/construction-industry/pipeline-of-projects/)

  Source checked 19 October 2026. Earlier pipeline reference. The project-specific row was not reverified on 27 October 2026. Use the project agency sources for current procurement information.

- [EnergyCo, Industry opportunities for the Hunter Transmission Project](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project/industry-opportunities)

  Source checked 27 October 2026.

- [EnergyCo, What we are building for the Hunter Transmission Project](https://www.energyco.nsw.gov.au/our-projects/hunter-transmission-project/transmission-infrastructure)

  Source checked 27 October 2026.

Project record checked 23 October 2026

Project information is indicative. It does not establish that a particular property is affected.

[Discuss this project : Hunter Transmission Project](https://stonepillar.com.au/contact/?matter=acquisition&project=hunter-transmission-project#enquiry) [Watch this project : Hunter Transmission Project](https://stonepillar.com.au/resources/nsw-project-watch/?watch=hunter-transmission-project#watch)

About the dates: the publication review records when this profile was approved for publication. Each official source has its own check date. The project record date refers to the catalogue entry. These dates do not establish that later project changes have been checked.

To cite this page: Stone & Pillar Legal, “Hunter Transmission Project”, NSW Project Watch, profile reviewed 27 October 2026, https\://stonepillar.com.au/resources/nsw-project-watch/hunter-transmission-project/

This page provides general information only. Project details may change and should be checked against official sources. The inclusion of a project on this page does not mean that any particular property will be acquired or affected. This page is not legal advice. Submitting an enquiry does not create a solicitor–client relationship, and any engagement is subject to conflict checks and written terms of engagement.

## Related project profiles

- [Central-West Orana Renewable Energy Zone (transmission)](https://stonepillar.com.au/resources/nsw-project-watch/central-west-orana-rez/)
- [Project EnergyConnect](https://stonepillar.com.au/resources/nsw-project-watch/energyconnect/)

[Find this project on the Project Watch hub](https://stonepillar.com.au/resources/nsw-project-watch/#project-hunter-transmission-project)

Where to start

## Discuss your project or land concern

Tell us what has happened and what decision you need to make. The preliminary call is to discuss whether Stone & Pillar can assist and the next step. If we can assist, scope and fees are agreed before substantive legal work begins.

[Request a call back](https://stonepillar.com.au/contact/?matter=acquisition#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=acquisition&project=hunter-transmission-project#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.