# Parramatta Light Rail Stage 2

Rail and metro · Greater Sydney · Transport for NSW

Documented stage: **Procurement / delivery**

Profile publication reviewed 27 October 2026. Individual source-check dates appear below. Inclusion does not establish that any particular property will be acquired or affected.

On this page

- [Project overview](https://stonepillar.com.au/resources/nsw-project-watch/parramatta-light-rail-stage-2/#overview)
- [Possible land impacts](https://stonepillar.com.au/resources/nsw-project-watch/parramatta-light-rail-stage-2/#land-impacts)
- [Documents to gather](https://stonepillar.com.au/resources/nsw-project-watch/parramatta-light-rail-stage-2/#documents)
- [Council areas](https://stonepillar.com.au/resources/nsw-project-watch/parramatta-light-rail-stage-2/#location)
- [Official sources](https://stonepillar.com.au/resources/nsw-project-watch/parramatta-light-rail-stage-2/#sources)

## Project overview

Parramatta Light Rail Stage 2 is a 10 kilometre extension from Stage 1 at Camellia to Sydney Olympic Park, with planning approval. Delivery is staged, with enabling works under construction.

- [NSW Government, Parramatta Light Rail Stage 2](https://www.nsw.gov.au/driving-boating-and-transport/projects/parramatta-light-rail/stage-2)
- [NSW Government, Stage 2 tracking to main construction (30 January 2026)](https://www.nsw.gov.au/ministerial-releases/parramatta-light-rail-stage-2-tracking-to-main-construction)

### Route and enabling works

The planned route passes through Rydalmere, Ermington, Melrose Park and Wentworth Point. Enabling works, including a public and active transport bridge across the Parramatta River between Melrose Park and Wentworth Point, have been under construction since 2025.

- [NSW Government, Parramatta Light Rail Stage 2](https://www.nsw.gov.au/driving-boating-and-transport/projects/parramatta-light-rail/stage-2)
- [NSW Government, Stage 2 tracking to main construction (30 January 2026)](https://www.nsw.gov.au/ministerial-releases/parramatta-light-rail-stage-2-tracking-to-main-construction)

### Stage 2a procurement and acquisitions

In January 2026 the NSW Government committed to Stage 2a, from Camellia to Wentworth Point, and said main works procurement would proceed alongside the commencement of property acquisitions. Main construction was expected to start in early 2027.

- [NSW Government, Stage 2 tracking to main construction (30 January 2026)](https://www.nsw.gov.au/ministerial-releases/parramatta-light-rail-stage-2-tracking-to-main-construction)

### Stage 2b investment decision

Stage 2b to Sydney Olympic Park remains subject to future investment decisions.

- [NSW Government, Parramatta Light Rail Stage 2](https://www.nsw.gov.au/driving-boating-and-transport/projects/parramatta-light-rail/stage-2)

## What this could mean for a property

Light rail is generally built along and beside existing roads and corridors. The project's answers to common questions say whole or partial acquisition of property will only occur where alternative options are not feasible, and the NSW Government said in January 2026 that property acquisitions would commence alongside main works procurement. Easements, temporary construction access, and business, parking and access effects near stops and work sites are also possible. A project near your property does not mean it will be acquired.

### Key things to watch

- The confirmed alignment and stop locations
- Whether your land or access is affected
- Any survey, valuation or acquisition correspondence
- Construction staging and access changes

### Possible land impacts

- Whole or partial acquisition of property where alternative options are not feasible
- Easements and temporary construction occupation
- Business, parking and access changes near stops and works
- Construction noise, vibration and amenity impacts

## Possible impact types

- Whole-property acquisition
- Partial acquisition
- Easement
- Temporary occupation
- Access change
- Business disturbance
- Noise / vibration / amenity

## Documents worth gathering

- Any letter or notice from the project
- Your title search and deposited plan
- Lease or licence documents for affected premises
- Business records, if a business is affected

## Location and relevant interests

**Council areas:** City of Parramatta.

**Often relevant to:** Owners and occupiers along the corridor; Businesses near stops and construction sites; Tenants and leaseholders.

## Related land guidance

- [My land is being acquired](https://stonepillar.com.au/issues/land-acquisition/)
- [Affected by a project](https://stonepillar.com.au/issues/affected-by-project/)
- [Compulsory acquisition](https://stonepillar.com.au/services/compulsory-acquisition/)

## Official sources

- [NSW Government, Parramatta Light Rail Stage 2](https://www.nsw.gov.au/driving-boating-and-transport/projects/parramatta-light-rail/stage-2)

  Source checked 27 October 2026.

- [NSW Government, Stage 2 tracking to main construction (30 January 2026)](https://www.nsw.gov.au/ministerial-releases/parramatta-light-rail-stage-2-tracking-to-main-construction)

  Source checked 27 October 2026.

- [Infrastructure NSW, Major Projects Pipeline (earlier catalogue reference)](https://www.infrastructure.nsw.gov.au/industry/construction-industry/pipeline-of-projects/)

  Source checked 19 October 2026. Earlier pipeline reference. The project-specific row was not reverified on 27 October 2026. Use the project agency sources for current procurement information.

Project record checked 19 October 2026

Project information is indicative. It does not establish that a particular property is affected.

[Discuss this project : Parramatta Light Rail Stage 2](https://stonepillar.com.au/contact/?matter=acquisition&project=parramatta-light-rail-stage-2#enquiry) [Watch this project : Parramatta Light Rail Stage 2](https://stonepillar.com.au/resources/nsw-project-watch/?watch=parramatta-light-rail-stage-2#watch)

About the dates: the publication review records when this profile was approved for publication. Each official source has its own check date. The project record date refers to the catalogue entry. These dates do not establish that later project changes have been checked.

To cite this page: Stone & Pillar Legal, “Parramatta Light Rail Stage 2”, NSW Project Watch, profile reviewed 27 October 2026, https\://stonepillar.com.au/resources/nsw-project-watch/parramatta-light-rail-stage-2/

This page provides general information only. Project details may change and should be checked against official sources. The inclusion of a project on this page does not mean that any particular property will be acquired or affected. This page is not legal advice. Submitting an enquiry does not create a solicitor–client relationship, and any engagement is subject to conflict checks and written terms of engagement.

## Related project profiles

- [Sydney Metro West](https://stonepillar.com.au/resources/nsw-project-watch/sydney-metro-west/)

[Find this project on the Project Watch hub](https://stonepillar.com.au/resources/nsw-project-watch/#project-parramatta-light-rail-stage-2)

Where to start

## Discuss your project or land concern

Tell us what has happened and what decision you need to make. The preliminary call is to discuss whether Stone & Pillar can assist and the next step. If we can assist, scope and fees are agreed before substantive legal work begins.

[Request a call back](https://stonepillar.com.au/contact/?matter=acquisition#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=acquisition&project=parramatta-light-rail-stage-2#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.