Practice area

# Compulsory acquisition and compensation

We act for owners, tenants, businesses and developers affected by compulsory acquisition in NSW, not for acquiring authorities. We act in negotiations with acquiring authorities and in compensation proceedings in the Land and Environment Court. An acquisition can affect your home, business premises or development long before compensation is settled. We advise on the interest being taken, the evidence needed to support your claim and the terms that will shape what happens next.

On this page

- [An approach, notice or project announcement](https://stonepillar.com.au/services/compulsory-acquisition/#first-steps)
- [Documents to collect](https://stonepillar.com.au/services/compulsory-acquisition/#documents)
- [How we assist](https://stonepillar.com.au/services/compulsory-acquisition/#how-we-assist)
- [Selected experience](https://stonepillar.com.au/services/compulsory-acquisition/#selected-experience)
- [Who can claim compensation](https://stonepillar.com.au/services/compulsory-acquisition/#who-can-claim-compensation)
- [The acquisition process](https://stonepillar.com.au/services/compulsory-acquisition/#the-acquisition-process)
- [If you have received a proposed acquisition notice](https://stonepillar.com.au/services/compulsory-acquisition/#if-you-have-received-a-proposed-acquisition-notice)
- [Reviewing an offer from Transport for NSW, Sydney Metro or another authority](https://stonepillar.com.au/services/compulsory-acquisition/#reviewing-an-offer-from-transport-for-nsw-sydney-metro-or-another-authority)
- [Heads of compensation](https://stonepillar.com.au/services/compulsory-acquisition/#heads-of-compensation)
- [Partial acquisitions, easements and retained land](https://stonepillar.com.au/services/compulsory-acquisition/#partial-acquisitions-easements-and-retained-land)
- [Business relocation and continuity](https://stonepillar.com.au/services/compulsory-acquisition/#business-relocation-and-continuity)
- [Valuation evidence](https://stonepillar.com.au/services/compulsory-acquisition/#valuation-evidence)
- [Class 3 proceedings](https://stonepillar.com.au/services/compulsory-acquisition/#class-3-proceedings)
- [From project investigation to acquisition](https://stonepillar.com.au/services/compulsory-acquisition/#pathway)
- [Common questions](https://stonepillar.com.au/services/compulsory-acquisition/#faq)
- [Legal framework](https://stonepillar.com.au/services/compulsory-acquisition/#legal-framework)
- [Related reading and situations](https://stonepillar.com.au/services/compulsory-acquisition/#related-reading)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=acquisition&service=compulsory-acquisition#schedule)

- Jurisdiction

  New South Wales

- Last updated

  21 November 2026

## An approach, notice or project announcement

- [A Proposed Acquisition Notice: the notice and next steps](https://stonepillar.com.au/issues/proposed-acquisition-notice/)
- [Acquisition or compensation correspondence: documents and dates](https://stonepillar.com.au/issues/land-acquisition/)
- [Understand the stage the project has reached](https://stonepillar.com.au/services/compulsory-acquisition/#pathway)

If a project has been announced but nothing has arrived yet, [NSW Project Watch](https://stonepillar.com.au/resources/nsw-project-watch/) lists public projects that may affect land, with the official source for each.

### What documents should I collect?

Have the following available for review once we confirm we can act:

- the title, deposited plan and leases or other occupation agreements
- every notice, offer and authority letter, with a record of when each was received
- the acquisition plan, easement terms and current project drawings
- valuations, planning approvals and evidence of development potential
- records of current access, services, operations and property condition
- business records, relocation options, quotations and invoices relevant to the claimed costs

Keep dated photographs and meeting notes. Identify which person or entity holds each interest and incurs each cost.

## How Stone & Pillar Legal can assist

We advise affected owners, tenants, businesses and developers on the acquisition process, compensation and related disputes. We review notices and offers, prepare claims with valuers and other advisers, negotiate terms and conduct Land and Environment Court proceedings.

The advice addresses the decision you need to make: whether the offer reflects the interest taken, how the remaining property can be used, what relocation requires and whether a dispute is worth pursuing.

- The land, the interest and the claimant

  Identify what will be taken, what remains and which person or entity holds each relevant interest.

- Notices and the acquisition timetable

  Distinguish project correspondence, proposed acquisition notices, acquisition notices and compensation notices, and identify the steps each requires.

- Valuation and expert evidence

  Settle focused briefs for valuers, planners, surveyors and other advisers, with the assumptions and evidence needed to test the claim.

- Compensation and settlement terms

  Assess the statutory categories alongside occupation, handover, releases and the timing of payments.

- Business continuity and relocation

  Connect relocation choices, approvals, fitout, operating constraints and supporting records to the compensation assessment.

- Partial acquisition and retained land

  Investigate access, loading, services, development yield and staging, and how the consequences affect the valuation of the land retained.

- Easements and temporary occupation

  Review the plan, restrictions, entry rights, duration and reinstatement obligations before agreement.

- Compensation objections and Court proceedings

  Advise on evidence, prospects, conciliation, settlement and litigation risk, and conduct Class 3 compensation proceedings.

Selected experience

## Compulsory acquisition and compensation experience

Michael's compulsory acquisition experience spans both sides of these matters, including time advising acquiring authorities in earlier government and major-firm roles. Stone & Pillar Legal acts for affected owners, businesses and developers, not for acquiring authorities. Having worked within the process gives the firm a practical understanding of how authorities assess, value and negotiate, which informs the way it prepares an owner's claim. His experience has included NSW Land and Environment Court Class 3 proceedings, Sydney Metro and WestConnex acquisitions, hospital and transport infrastructure projects, easement and partial acquisitions, business disturbance issues, _Roads Act 1993_ powers of entry, and strategic input on valuation evidence and compensation.

A selection of matters Michael has advised or acted on over his career, many in earlier roles in private practice and government before he founded Stone & Pillar Legal. They are listed as evidence of relevant experience, not as retainers of the firm.

- ### Sydney Metro, proposed Sydney Science Park

  Acted in compensation proceedings concerning Sydney Metro's compulsory acquisition affecting land at the proposed Sydney Science Park.

  - Authority:

    Sydney Metro

  - Client / party:

    Landowner / developer

  - Class 3 involvement:

    Yes

- ### Sydney Metro, 9 Hunter Street

  Advised on compensation issues arising from Sydney Metro's compulsory acquisition of 9 Hunter Street.

  - Authority:

    Sydney Metro

  - Client / party:

    Commercial property interest

  - Class 3 involvement:

    Yes

- ### Gaudioso / Parramatta Road, Camperdown

  Acted in a WestConnex compensation valuation dispute concerning acquired commercial properties on Parramatta Road.

  - Authority:

    Transport for NSW / RMS

  - Class 3 involvement:

    Yes

Selected experience is provided as a general indication of relevant matter exposure. Past matters do not imply that the same outcome will be available in any future matter. Each acquisition, valuation and compensation claim depends on its own statutory context, facts, evidence and deadlines.

[Further experience](https://stonepillar.com.au/about/experience/#further-experience)

A compensation figure is only part of the decision. An owner may need to replace a home. A business may need premises with the right approvals, power supply and customer access. A developer may be left with a smaller site, altered access or an unworkable staging plan. The legal work must address those practical consequences while keeping the claim within the statutory rules.

## Who can claim compensation

Under the _Land Acquisition (Just Terms Compensation) Act 1991_ (NSW), compensation is payable to the holder of an interest in land that an acquisition notice divests, extinguishes or diminishes. That can include a tenant as well as a registered owner. A business does not qualify merely because a project affects its trade: its interest in the acquired land and the basis of each claimed cost need to be established.

We identify the relevant interests and claimants at the outset. Where one company owns the property and another operates the business, their positions need separate attention. Leases, occupation arrangements, easements and the acquisition plan can be as important as the title search.

Read our [compulsory acquisition and compensation issue overview](https://stonepillar.com.au/issues/land-acquisition/) .

## The acquisition process

An authority will generally negotiate before beginning compulsory acquisition. Section 10A ordinarily requires a genuine attempt to acquire by agreement for at least six months before a proposed acquisition notice. There are exclusions, including specified underground acquisitions, and circumstances in which the period may change or the requirement does not apply.

A [proposed acquisition notice](https://stonepillar.com.au/issues/proposed-acquisition-notice/) gives notice of an intended compulsory acquisition. The usual minimum notice period is 90 days, although the Act permits a shorter period by written agreement or ministerial approval. The notice does not itself transfer the land. Compulsory acquisition takes effect through publication of an acquisition notice in the NSW Government Gazette; compensation can remain unresolved after that occurs.

The compensation notice is different again. It states the acquiring authority’s offer based on the Valuer-General’s determination and is the notice relevant to the usual 90-day compensation objection period. A negotiated offer, a proposed acquisition notice and a compensation notice should never be treated as interchangeable.

## If you have received a proposed acquisition notice

A proposed acquisition notice does not transfer the land, and it is not an offer of compensation. It starts the notice period before the authority can acquire the land compulsorily. The first steps are to confirm the interest the notice covers, the land shown on the acquisition plan and the date the notice was given, and then to read what the notice and the documents served with it ask of you, and by when.

Read our [proposed acquisition notice issue overview](https://stonepillar.com.au/issues/proposed-acquisition-notice/) .

## Reviewing an offer from Transport for NSW, Sydney Metro or another authority

The stage at which an offer is made decides what it is. An offer made while the authority negotiates to acquire the land by agreement is a negotiated offer, and its written terms decide what is paid, when, and what is given up in return. The offer in a compensation notice is the authority’s offer based on the Valuer-General’s determination, and it is the offer the 90-day objection period runs from.

A review of either kind of offer asks the same questions:

- which interest is being acquired, and whether the figure covers each head of compensation that applies;
- what the authority’s valuation assumes about planning controls, development potential and the effect of the project;
- how any retained land, easement or access change has been treated;
- when payment and possession occur, and whether a relocation can work to that timetable;
- whether accepting the offer releases other claims.

We act for the person whose land is being acquired, not for the authority making the offer.

## Heads of compensation

Section 55 identifies six matters. Each has its own test; the claim is not simply the market value of the area taken plus every consequence of the project.

- **Market value:** the value at the acquisition date under section 56. The statutory assessment disregards specified effects, including increases or decreases caused by the project for which the land is acquired.
- **Special value:** a financial advantage additional to market value that is incidental to the claimant’s use of the land. Personal attachment alone is not special value.
- **Severance:** a reduction in the market value of the claimant’s other land caused by its severance from that person’s land.
- **Disturbance:** costs falling within section 59, including eligible professional costs, relocation costs and specified other financial costs. The statutory connection to the acquisition and the requirements for each category must be established.
- **Disadvantage resulting from relocation:** non-financial disadvantage from having to relocate a principal place of residence because of the acquisition. It is subject to statutory conditions and an indexed maximum; it is not a general payment for business disruption.
- **Changes in the value of other land:** increases as well as decreases in the value of the claimant’s adjoining or severed land caused by the public purpose, or its proposal. A decrease is often described as injurious affection.

The categories must be considered together. Section 61 can exclude particular amounts for special value or disturbance where market value is assessed on a different potential use. A valuation based on redevelopment therefore needs to be checked against claims arising from the existing use.

Underground easements and tunnel acquisitions can also engage special compensation rules, including under the legislation authorising the acquisition.

Read our [compulsory acquisition and compensation issue overview](https://stonepillar.com.au/issues/land-acquisition/) .

## Partial acquisitions, easements and retained land

A narrow strip of land can have consequences well beyond its area. The remaining site may need different vehicle movements, loading arrangements, drainage, setbacks or services. Development yield and staging may need to be reconsidered. The task is to establish what changes, why it changes and how that bears on the statutory valuation and compensation questions.

For an easement, the plan and the legal terms must be read together. Width and location are only the beginning: access rights, maintenance, restrictions on building or planting, relocation of services and reinstatement may determine what you can do with the property. Proposed works and permanent rights also need to be distinguished from temporary access or occupation arrangements.

Read our [partial acquisitions and retained land issue overview](https://stonepillar.com.au/issues/partial-acquisitions/) .

## Business relocation and continuity

Relocation requires a workable program as well as a cost schedule. Replacement premises may need planning approval, licensing, fitout or substantial utility upgrades before trading can resume. Lease expiry, make-good obligations, plant removal, stock, staff and customer access all affect the choices available.

The handover date, payment timetable and date operations can lawfully begin at replacement premises need to be considered together. A gap between them can affect both the interruption to trade and the funds needed to make the move.

We work with the relevant advisers to distinguish what the business needs to do from what it can claim, and to check the evidence and statutory basis for each claimed item. Keep records of current operations, alternative sites considered, quotations, invoices and the reasons for relocation decisions. A drop in turnover or a forecast profit shortfall does not, by itself, establish a compensable financial cost under section 59. Avoid assuming that every business loss, replacement-property duty payment or financing expense will be reimbursed.

Read our [business relocation after acquisition issue overview](https://stonepillar.com.au/issues/business-relocation/) .

## Valuation evidence

A useful valuation answers the statutory question for the interest acquired. It should explain the method, comparable evidence and assumptions about planning controls, development potential, timing and cost. Where land is retained, the assessment also needs to address the relevant effects on that land.

For a development site, an asserted yield needs support from the planning and physical constraints. For an operating property, the evidence must distinguish the value of the property interest from the business’s claimed costs. The brief to each expert should identify the issue they are being asked to resolve, so that the work is proportionate and the assumptions can be tested.

Before pausing design work, a planning application or construction because acquisition is expected, consider the valuation consequences. The rule requiring specified project effects to be disregarded does not automatically value the property as though those steps had continued. [_Sydney Metro v G & J Drivas Pty Ltd_ \[2024\] NSWCA 5](https://www.caselaw.nsw.gov.au/decision/18d5868626aa8267ce013eb7) distinguishes effects caused by the public purpose from effects caused only by an owner’s response to the prospect of acquisition.

A [compensation objection differs from an appeal against a land valuation](https://stonepillar.com.au/valuation-and-compensation-objections/) . The decision, statutory pathway and evidence should be identified before a proceeding is commenced.

Read our [acquisition valuation evidence issue overview](https://stonepillar.com.au/issues/acquisition-valuation/) .

## Class 3 proceedings

A person who has claimed compensation may generally object to the amount offered in the compensation notice by lodging an objection in the Land and Environment Court within 90 days after receiving that notice. Section 66 provides a limited late-objection pathway requiring good cause; it should not be treated as an extension available on request. Rejection of a claim without a compensation notice involves a separate pathway under section 67.

If a person entitled to compensation neither accepts the offer nor lodges an objection within 90 days after receiving the compensation notice, the offer is generally taken to be accepted. The Court must be satisfied of good cause for a late objection.

The Court determines compensation in its Class 3 jurisdiction. Negotiation and conciliation can continue, but the evidence must be prepared for determination if agreement is not reached. An objection to compensation does not itself challenge the legality of the acquisition or prevent it taking effect.

Proceedings involve time, expert work and costs risk. The authority may contend for less than its statutory offer, and the Court may determine a lower amount. Section 66(4) also allows the Court to cancel or reduce interest accruing after proceedings begin if the compensation, excluding interest, does not exceed the authority’s offer by more than 10%.

Court costs are discretionary, and settlement offers and the conduct of the proceeding can affect the costs order. We assess those risks alongside the amount in dispute, the available evidence and the practical value of a negotiated resolution.

Read our [compensation objections issue overview](https://stonepillar.com.au/issues/compensation-objections/) .

Before a notice arrives

## A public project can begin affecting a property long before formal acquisition

Route selection, design, environmental assessment and investigation access may begin well before a proposed acquisition notice. Those early stages can reveal whether a project may need permanent land, an easement, a construction compound or temporary access, and whether existing access or operations may change.

Use that time to check the official documents, record current use and condition, and identify the rights and operational arrangements that matter. The stages below can overlap; they are an outline of the process, not a fixed sequence for every project.

1. 1

   ### Project investigation and design

   Published routes, designs and project documents help identify the land and interests that may be affected. A project announcement is not an acquisition notice.

2. 2

   ### Assessment, exhibition and access requests

   Check the proposed impacts, submission opportunities and the legal basis of any survey or investigation access. These processes can overlap with acquisition planning.

3. 3

   ### Negotiation and acquisition by agreement

   The authority generally seeks agreement before compulsory acquisition. Review the price, rights acquired, handover, occupation and relocation terms together.

4. 4

   ### Proposed acquisition notice

   This gives notice of an intended compulsory acquisition. It does not itself transfer the land, and negotiation can continue.

5. 5

   ### Acquisition notice in the Gazette

   Publication effects the compulsory acquisition. The interest described in the notice matters; compensation may still be unresolved.

6. 6

   ### Valuer-General determination

   Identify the claimants and prepare and lodge the claim and supporting evidence during the earlier stages. For a compulsory acquisition, the Valuer-General determines the compensation to be offered; the determination may be made before or after acquisition.

7. 7

   ### Compensation notice and objection

   Distinguish the statutory compensation notice from an earlier offer. Receipt of that notice is the trigger for the usual 90-day objection period under section 66.

8. 8

   ### Negotiation, conciliation or Court determination

   Test the evidence and settlement terms against the costs, time and risks of a Class 3 proceeding. A compensation dispute and a challenge to the acquisition's legality are different matters.

Questions

## Common questions

How do I know whether my property may be acquired?

Correspondence from the acquiring authority and the published project plans are the starting points. Check the interest and area identified, not just whether your address falls near a route. An announcement, corridor or investigation area does not itself mean that your property will be acquired.

Can a project affect my property before a proposed acquisition notice?

Yes. Designs, environmental assessment, access requests and negotiations can raise practical issues before the compulsory process begins. Preserve evidence of the property's existing use, condition and access. Check any submission opportunity separately from the acquisition process. Where land is formally designated for acquisition, an eligible owner may be able to require earlier acquisition on statutory hardship grounds; designation, ownership and hardship requirements must be met.

What is a proposed acquisition notice?

It is written notice of an intention to acquire land compulsorily under the _Land Acquisition (Just Terms Compensation) Act 1991_ (NSW). It usually precedes acquisition by at least 90 days, subject to the Act's shorter-period provisions. It does not itself transfer the land. The later compensation notice is a different document with a different legal purpose.

[Proposed acquisition notices and next steps](https://stonepillar.com.au/issues/proposed-acquisition-notice/)

What if only part of my land is required?

Assess both the interest taken and the land retained. Severance and the increase or decrease in value of adjoining or severed land caused by the public purpose are distinct statutory matters. Evidence may need to address access, services, loading, development yield and staging. A project impact does not automatically translate into an additional compensation item.

What if the project only requires an easement?

The plan and easement terms determine the rights taken and the restrictions left on the property. Check building and planting restrictions, entry and maintenance rights, services and reinstatement. The compensation rules depend on the interest and statutory scheme; underground rights and tunnel acquisitions can have special limitations.

What if the authority wants access for surveys or investigations?

Identify whether access is sought by agreement or under a statutory power. Review the notice or proposed agreement, the work, timing, access routes, insurance, damage and reinstatement arrangements. Record the property's condition before entry. Investigation access does not itself establish that the property will be acquired.

Can a tenant or business claim compensation?

A tenant may hold a compensable interest even though it does not own the freehold. Identify the lease or other interest affected, the legal entity holding it and the person incurring each claimed cost. Business disturbance is subject to section 59; the fact that trade is affected is not enough to establish a claim. Informal occupation arrangements require particular care.

What if my business is affected but no interest in my land is acquired?

Disruption from nearby construction does not by itself create an entitlement to acquisition compensation. The cause of the impact, the rights affected and the legislation or agreement governing the works need separate assessment. Keep records of access changes, incidents and financial effects, but do not assume that every trading loss will be reimbursed.

Should I speak to the acquiring authority before getting advice?

Early communication can help establish what is proposed. Before agreeing to a price or signing an access agreement, acquisition agreement or release, understand the rights affected and the obligations you would accept. Obtain a written record of proposed terms, including any assurance about costs, occupation or relocation.

What should I do with a compensation offer from an acquiring authority?

Before accepting an offer from an acquiring authority such as Transport for NSW or Sydney Metro, check what it covers against each relevant head of compensation, such as market value, special value, severance, disturbance and disadvantage resulting from relocation, and what valuation evidence supports it. Check what accepting or signing would settle, including any release of other claims and any terms about costs, occupation or relocation. An offer that is neither accepted nor objected to within the statutory period is generally taken to be accepted: see the answer on objecting to the amount of compensation below.

[Who pays the costs of a compensation claim](https://stonepillar.com.au/issues/land-acquisition/)

Can I object to the amount of compensation?

Under section 66, a person who has claimed compensation may lodge an objection in the Land and Environment Court within 90 days after receiving the compensation notice. If a person entitled to compensation neither accepts the offer nor objects within 90 days after receiving the notice, the offer is generally taken to be accepted. A late objection requires the Court to be satisfied of good cause. Without a compensation notice, a claim may be taken to be rejected after 60 days without being dealt with. The ordinary section 67 appeal period is 90 days after actual or deemed rejection; a late appeal requires good cause. Negotiation should not be treated as extending a statutory period.

Does a compensation objection stop the acquisition?

No. The section 66 process determines compensation; the acquisition can take effect before the amount is resolved. A challenge to the lawfulness of the acquisition raises different questions about the power and process used. Seek separate advice promptly: available steps and remedies depend on the stage reached.

These answers are general information only and are not legal advice.

## Key legal framework

Matters in this area may involve, depending on the facts, among others:

- [_Land Acquisition (Just Terms Compensation) Act 1991_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1991-022)
- [_Roads Act 1993_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1993-033)
- [_Environmental Planning and Assessment Act 1979_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1979-203)
- [_Land and Environment Court Act 1979_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1979-204)

Which provisions apply depends on the facts. General information only, not legal advice.

## Related reading

- [My land is being acquired — Compulsory acquisition in NSW: negotiations and valuation — How to approach the six-month negotiation period, acquisition-date valuation, project effects and the terms of an agreement for compulsory acquisition in NSW.](https://stonepillar.com.au/insights/just-terms-compensation-basics/)
- [My land is being acquired — Compulsory acquisition in NSW: the PAN and compensation notice — What to do after a Proposed Acquisition Notice in NSW: the compensation claim, possession, Court objection period, costs and advance payments.](https://stonepillar.com.au/insights/compulsory-acquisition-pan-compensation-notice/)
- [My land is being acquired — Choosing a lawyer for a compulsory acquisition claim in NSW — How a NSW landowner chooses a compulsory acquisition lawyer: the work at each stage, who the lawyer acts for, who runs the claim, costs and the Court.](https://stonepillar.com.au/insights/choosing-a-compulsory-acquisition-lawyer-nsw/)

[All articles on compulsory acquisition](https://stonepillar.com.au/insights/topic/compulsory-acquisition/)

## Related situations

- [My land is being acquired](https://stonepillar.com.au/issues/land-acquisition/)
- [Affected by a project](https://stonepillar.com.au/issues/affected-by-project/)
- [Partial acquisitions and retained land](https://stonepillar.com.au/issues/partial-acquisitions/)
- [Business relocation after acquisition](https://stonepillar.com.au/issues/business-relocation/)
- [Acquisition valuation evidence](https://stonepillar.com.au/issues/acquisition-valuation/)
- [Compensation objections](https://stonepillar.com.au/issues/compensation-objections/)
- [I received a PAN](https://stonepillar.com.au/issues/proposed-acquisition-notice/)
- [Blighted by future acquisition](https://stonepillar.com.au/issues/hardship-acquisition/)

This page is general information only and is not legal advice. It may not be current, and how the law applies depends on the specific facts. For advice on your situation, contact Stone & Pillar Legal.

Where to start

## Legal support for your acquisition

Tell us how the acquisition affects your land or business and the stage it has reached. On a short preliminary call we can tell you whether we can assist and what the first step would be.

[Request a call back](https://stonepillar.com.au/contact/?matter=acquisition&service=compulsory-acquisition#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=acquisition&service=compulsory-acquisition#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.