Practice area

# Council orders, notices and local government

A notice or order from a council or regulator can carry real obligations and short timeframes. We advise on the power to issue it, the statutory process, what it requires and the options for compliance, representations or appeal.

- Jurisdiction

  New South Wales

- Last updated

  10 November 2026

New South Wales

Notices and orders that affect land and buildings.

On this page

- [Advice on a council notice or order](https://stonepillar.com.au/services/council-notices/#advice-on-a-council-notice-or-order)
- [Identifying the notice and the recipient](https://stonepillar.com.au/services/council-notices/#identifying-the-notice-and-the-recipient)
- [Notices of intention and representations](https://stonepillar.com.au/services/council-notices/#notices-of-intention-and-representations)
- [Compliance dates and appeal periods](https://stonepillar.com.au/services/council-notices/#compliance-dates-and-appeal-periods)
- [Stop work, fire safety and continuing operations](https://stonepillar.com.au/services/council-notices/#stop-work-fire-safety-and-continuing-operations)
- [Orders affecting locally listed heritage items](https://stonepillar.com.au/services/council-notices/#orders-affecting-locally-listed-heritage-items)
- [Clean-up, prevention and title implications](https://stonepillar.com.au/services/council-notices/#clean-up-prevention-and-title-implications)
- [Appeals, costs and a proportionate response](https://stonepillar.com.au/services/council-notices/#appeals-costs-and-a-proportionate-response)
- [Preparing for an initial discussion](https://stonepillar.com.au/services/council-notices/#preparing-for-an-initial-discussion)
- [Common questions](https://stonepillar.com.au/services/council-notices/#questions)

How we help

- Development control orders (_Environmental Planning and Assessment Act 1979_, Schedule 5)
- Orders under the _Local Government Act 1993_
- Stop work, demolish works and repair orders
- Orders and unauthorised works affecting locally listed heritage items
- Fire safety orders and building compliance
- Clean-up and prevention notices (_Protection of the Environment Operations Act 1997_)
- Notices of intention and representations
- Cost-recovery notices after council works
- Appeals and review in the Land and Environment Court

For owners, occupiers and businesses that have received a council order or notice in New South Wales.

A council notice can interrupt construction, restrict a business or require work to an occupied building. The immediate task is to identify the legal power, the evidence supporting its use, what must be done and which dates govern the process. The heading alone may not answer those questions.

We advise on preparing and assessing notices and orders, responding to them, resolving compliance issues and conducting appeals.

If you are responding to a government investigation or enforcement action, or questioning how a decision was made, see our [administrative law and government enforcement practice](https://stonepillar.com.au/services/administrative-law/) .

## Advice on a council notice or order

Start with the document’s title, the council that issued it, when you received it and any date it states. Tell us whether the issue affects building work, use of premises, fire safety or an environmental concern.

We can discuss the scope of a first review and whether technical input is likely to be needed. Keep the complete document and attachments to hand for the call; do not upload confidential or privileged material with the initial enquiry.

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=council&service=council-notices#schedule) [Request a call back](https://stonepillar.com.au/contact/?matter=council&service=council-notices#enquiry)

The preliminary call is intended to discuss whether we can assist and the scope of a possible first step. It is not intended to provide legal advice. Ask us to confirm in writing any work we agree to undertake. Tell us any response date or deadline. If it is close, call (02) 8014 5817 and do not wait for an online response to seek advice.

For an EPA or council environmental notice, see our [environmental regulation service](https://stonepillar.com.au/services/environmental-regulation/) . For a development application decision, see [planning and development](https://stonepillar.com.au/services/planning-development/) .

## Identifying the notice and the recipient

The legislation determines the available powers and safeguards. Common matters include:

- **Development control orders** under Schedule 5 of the _Environmental Planning and Assessment Act 1979_ (NSW), including stop work, stop use, demolish works and fire safety orders.
- **Council orders** under section 124 of the _Local Government Act 1993_ (NSW), which specifies the circumstances and people to whom each order may apply.
- **Clean-up and prevention notices** under the _Protection of the Environment Operations Act 1997_ (NSW), including notices given by a council or the EPA. The relevant power determines who may issue the notice and to whom. The EPA also has power to issue a clean-up notice in an emergency.
- **Cost recovery**, where an authority seeks payment for action taken or costs incurred under its statutory powers.

An owner, tenant, operator or contractor may have a different role under the relevant power. A private agreement about who pays for repairs does not, by itself, answer whether the authority has addressed the correct person. The property records, lease, approvals and actual activity may all matter.

The [Notice Decoder](https://stonepillar.com.au/navigator/tools/notice-decoder/) can help identify a document. The complete notice, its attachments and the circumstances of service remain essential to legal advice.

Read our [council notices and orders issue overview](https://stonepillar.com.au/issues/council-notices/) .

## Notices of intention and representations

A notice of intention ordinarily gives an opportunity to respond before a proposed order is made. It should be distinguished from an operative order requiring compliance. Advance notice is not always required. The Schedule 5 notice and representation process generally excludes stop work orders, specified fire safety orders, orders expressed to be given in an emergency and specified State significant infrastructure orders.

Representations can address the factual basis, the person responsible, the work proposed and the time reasonably needed. The useful response is often a supported alternative: an engineer’s scope, a fire safety strategy, evidence of an existing consent or a staged program that addresses the identified risk.

The authority must consider representations where the statutory process requires it. It may nevertheless make an order. Discussions should therefore proceed alongside preparation for the next decision, particularly where contractors, tenants or an operating business will be affected.

Read our [representations before a decision issue overview](https://stonepillar.com.au/issues/administrative-representations/) .

## Compliance dates and appeal periods

A response date, a compliance date and the last day to appeal serve different purposes. Each needs to be identified separately. An appeal period is not extra time to comply, and an informal request for more time should not be treated as changing either deadline.

Development control orders, Local Government Act orders and environmental notices have different appeal pathways and time limits. The document, statutory power, service history and any later order or variation need to be checked. A response date or compliance date is not necessarily the last day to appeal. Seeking more time or lodging an appeal does not itself establish that compliance can be postponed.

An appeal does not automatically suspend a development control order, a Local Government Act order or a prevention notice. If suspension is needed, the Court’s power to grant a stay must be considered separately. A stay is not guaranteed; immediate safety and environmental risks remain important.

Read our [council notices and orders issue overview](https://stonepillar.com.au/issues/council-notices/) and [stays and interim orders issue overview](https://stonepillar.com.au/issues/interim-relief/) .

## Stop work, fire safety and continuing operations

Some orders can require immediate compliance. A stop work or cease-use direction needs to be read closely to establish its scope. Do not assume it affects only the particular activity mentioned in earlier discussions with an officer.

For an occupied building or business, the response may need to address safe access, essential services, stock, residents, customers and contractor availability. Technical evidence should explain the risk and the proposed remedial work, including whether work can sensibly be staged. Operational inconvenience alone does not answer a safety concern or establish that an order is unlawful.

An application to approve or retain work is not, by itself, a suspension of an existing order. The approval strategy and the enforcement response need to be considered together.

Work required to comply with a development control order does not require an application for consent or approval under the _Environmental Planning and Assessment Act 1979_ (NSW): [Schedule 5, clause 29](https://legislation.nsw.gov.au/view/html/inforce/current/act-1979-203#sch.5-sec.29) makes that distinction. It does not provide the same exemption for additional work merely undertaken at the same time. Requirements under other legislation, including heritage controls where applicable, still need to be checked.

Read our [stop work and fire safety orders issue overview](https://stonepillar.com.au/issues/stop-work-fire-safety/) .

## Orders affecting locally listed heritage items

An order to repair, alter or demolish a locally listed building needs to be considered alongside the item’s heritage significance and the statutory power being used. We examine the listing, the order’s exact requirements, existing consents and any heritage or structural evidence. The response may need to address both an immediate safety concern and the effect of the proposed work on significant fabric.

For development control orders, Schedule 5 of the _Environmental Planning and Assessment Act 1979_ (NSW) contains specific provisions for heritage items. The authority’s heritage considerations and any procedural exceptions depend on the order and circumstances. We assess those requirements when preparing representations, proposing an alternative scope of work or considering an appeal.

The consent exception for work required by a development control order is confined to that work and to the planning Act. It should not be treated as permission for a wider renovation or as an exemption from separate Heritage Act requirements. We distinguish mandatory work from additional work proposed at the same time and advise on the approvals each needs.

Where work has already started without the necessary approval, we advise on the enforcement response, evidence preservation and options for future work. An application or discussion with council should not be treated as permission to continue, or as resolving liability for past work.

Read our [heritage approvals issue overview](https://stonepillar.com.au/issues/heritage-approvals/) and [unauthorised works issue overview](https://stonepillar.com.au/issues/unauthorised-works/) .

## Clean-up, prevention and title implications

A pollution notice can require investigation, containment, changed operating practices or remedial work, depending on the power used and its terms. Identifying the source of the problem and preserving the evidence can be as important as designing the immediate response.

Clean-up and prevention notices may be registered in relation to affected land under the _Protection of the Environment Operations Act 1997_ (NSW). Registration therefore matters in a purchase, finance or leasing review. Completion of work should not be assumed to remove a registered notice automatically; the registration and any application for its variation or removal need attention.

Development control orders can bind successors and continue beyond their compliance deadline. Separately, a registered compliance cost notice under the _Protection of the Environment Operations Act 1997_ (NSW) can secure payment through a charge over land the recipient owns, subject to the statutory cessation rules. The statutory basis and title consequences of each notice need to be checked separately.

If an appropriate regulatory authority or the EPA has given a clean-up notice, it may also restrict access to premises or a substance where the statutory grounds are met. Advice on the notice should account for what that means for the site’s operations as well as the required clean-up action.

An access restriction can take effect on publication on a NSW Government website or, in an emergency, on prominent display in or adjacent to the premises, without prior personal service.

Read our [clean-up and prevention notices issue overview](https://stonepillar.com.au/issues/epa-notice/) .

## Appeals, costs and a proportionate response

Depending on the power, the available course may be representations, compliance, a variation, a merits appeal or a challenge to legal validity. Those routes answer different questions. We assess the authority’s power, the evidence supporting the requirements and whether a narrower or differently staged response is available.

Proceedings can add legal fees, expert costs, delay and uncertainty. The Court may uphold the order, and a costs order may be made where the applicable rules permit. The likely benefit must justify the expense of the dispute.

For a development control order, section 8.19 permits the Court to award compensation for expenses caused by an unsubstantiated order or unreasonable terms. The remedy is discretionary. A compensation claim has its own time limit, which depends on whether an appeal was made. Seek advice promptly on the order and any appeal decision.

Non-compliance can expose a recipient to penalties and, under relevant powers, the authority carrying out work and recovering its costs. A recovery demand should be examined against the statutory basis, the work undertaken and the amounts claimed. It is distinct from the legal costs of Court proceedings.

Read our [council notices and orders issue overview](https://stonepillar.com.au/issues/council-notices/) .

## Preparing for an initial discussion

Have the proposed or issued notice and attachments, any record of service, the property address and relevant dates to hand. Existing approvals, photographs, technical reports and a short account of the activity or works will help identify what advice is needed.

Please provide only a brief outline and the names of the relevant parties for the initial enquiry. Keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in the documents. Do not assume that sending an enquiry or making a booking protects a deadline. Ask us to confirm the work we have agreed to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice rather than waiting for an online reply.

The principal sources include [Schedule 5 and Part 8 of the _Environmental Planning and Assessment Act 1979_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1979-203) , [Chapter 7 of the _Local Government Act 1993_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1993-030) and the [_Protection of the Environment Operations Act 1997_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1997-156) .

This page is general information only and is not legal advice. It may not be current, and how the law applies depends on the specific facts. For advice on your situation, contact Stone & Pillar Legal.

## Council orders, notices and regulatory action

Tell us about the order, notice or proposed action, the authority involved and any stated date. We can discuss whether the firm can assist and the proposed next step.

The preliminary call covers

- What has happened and the decision you need to make
- The authority or other party involved, so we can check for conflicts
- Any date stated in the documents you have received
- Whether the firm can assist, and what a scoped first step would involve

Tell us which document you received, who issued it and any date it states. Keep it to hand for the call.

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=council&service=council-notices#schedule)

[Request a call back](https://stonepillar.com.au/contact/?matter=council&service=council-notices#enquiry)

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

Prefer to talk? [(02) 8014 5817 ](tel:+61280145817)· [Email](mailto:enquiries@stonepillar.com.au)

Your enquiry will be reviewed by Michael Themis , Principal Solicitor of Stone & Pillar Legal.

## Key legal framework

Matters in this area may involve, depending on the facts, among others:

- [_Environmental Planning and Assessment Act 1979_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1979-203)
- [_Local Government Act 1993_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1993-030)
- [_Protection of the Environment Operations Act 1997_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1997-156)
- [_Land and Environment Court Act 1979_ (NSW)](https://legislation.nsw.gov.au/view/html/inforce/current/act-1979-204)

Which provisions apply depends on the facts. General information only, not legal advice.

Related situations

- [Council notice or order](https://stonepillar.com.au/issues/council-notices/)
- [Unauthorised works or use](https://stonepillar.com.au/issues/unauthorised-works/)
- [Stop work and fire safety orders](https://stonepillar.com.au/issues/stop-work-fire-safety/)
- [Heritage constraints](https://stonepillar.com.au/issues/heritage-approvals/)

## Common questions

- What can representations about a proposed order address?

  Representations can address the factual basis, the person responsible, the work proposed and the time reasonably needed. The useful response is often a supported alternative: an engineer's scope, a fire safety strategy, evidence of an existing consent or a staged program that addresses the identified risk.

- What should a response address for an occupied building or business?

  For an occupied building or business, the response may need to address safe access, essential services, stock, residents, customers and contractor availability. Technical evidence should explain the risk and the proposed remedial work, including whether work can sensibly be staged.

- What should I have ready for an initial discussion?

  Have the proposed or issued notice and attachments, any record of service, the property address and relevant dates to hand. Existing approvals, photographs, technical reports and a short account of the activity or works will help identify what advice is needed. Please provide only a brief outline and the names of the relevant parties for the initial enquiry. Keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in the documents. Do not assume that sending an enquiry or making a booking protects a deadline. Ask us to confirm the work we have agreed to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice rather than waiting for an online reply.

These answers are general information only and are not legal advice.

Where to start

## Discuss a response to your council notice

Start with a brief outline of the notice and where matters stand with council. On a short preliminary call we can tell you whether we can assist and what the first step would be.

[Request a call back](https://stonepillar.com.au/contact/?matter=council&service=council-notices#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=council&service=council-notices#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.