Land access and easements

# Section 88K easements

An easement dispute can determine whether land can be developed and how neighbouring land can be used. We advise on seeking an easement, responding to a proposed easement and negotiating terms before court proceedings become necessary.

- Jurisdiction

  New South Wales

- Last updated

  12 November 2026

## When the Court can impose an easement

Section 88K of the _Conveyancing Act 1919_ (NSW) allows the Supreme Court to impose an easement over one property for the benefit of another. The easement must be reasonably necessary for the effective use or development of the land that will benefit. An owner's refusal to agree does not, by itself, establish that test.

The Court must also be satisfied that:

- the proposed use of the benefiting land is not inconsistent with the public interest;
- the owner and other people with relevant registered interests in the burdened land can be adequately compensated for the loss or disadvantage caused; and
- all reasonable attempts to obtain the easement, or an easement having the same effect, have been unsuccessful.

These requirements call for a properly defined proposal and supporting evidence. A court order is not automatic. The location, dimensions and terms of the right matter as much as the reason it is sought.

## If you need an easement

Start with the use or development you propose, the right it requires and the available alternatives. A drainage connection, vehicle access route or service corridor may raise different engineering, planning and title questions. We assess those questions together before recommending a negotiation or application.

We review title documents and plans, the proposed easement terms, development approvals and the technical reasons for the proposed route. Where needed, we work with surveyors, engineers, planners and valuers to identify the evidence required and the likely effect on the neighbouring land.

## If an easement is sought over your land

A request should be assessed against both the statutory test and the practical consequences for your property. We examine whether the proposed right is justified, whether a different route or narrower right should be considered, and how construction and future use would affect your land.

The assessment may include access, privacy, security, existing services, maintenance responsibilities and constraints on future development. We advise on the response, evidence and negotiating position, including whether the proposal should be opposed or resolved on different terms.

## Negotiations and workable terms

Section 88K requires all reasonable attempts to obtain the right to have been unsuccessful. A useful negotiation therefore needs more than a demand for access: the other owner should be able to understand the proposed area, permitted use, works and terms, and the basis of any compensation offer.

We help prepare or respond to proposals and keep an accurate record of offers, counterproposals and the reasons agreement has not been reached. Draft terms should address construction access, repair and maintenance, insurance, reinstatement and any proposed relocation arrangements. The aim is a right that can operate sensibly over time.

## Compensation, costs and commercial judgment

Under section 88K(4), the Court must provide for compensation to the owner and other relevant registered interest holders, unless it determines that compensation is not payable because of the special circumstances of the case. The question is the loss or other disadvantage caused by imposing the easement, not simply the area of land within the proposed route.

Section 88K(5) ordinarily places the costs of the proceedings on the applicant, unless the Court orders otherwise. That is a significant consideration for an applicant and is not a promise that an affected owner will recover every expense. Legal costs, expert fees, compensation, delay and the uncertainty of litigation should be assessed together.

Before recommending proceedings, we consider the value of the proposed right, the strength of the evidence and whether a negotiated outcome or alternative design is commercially preferable.

## The right court and procedure

Section 88K applications are ordinarily brought in the Supreme Court. Section 40 of the _Land and Environment Court Act 1979_ (NSW) gives the Land and Environment Court a related power in specified circumstances involving a development consent appeal. It is not a general alternative forum for every easement dispute.

We check the proposed right, the planning proceedings and the available jurisdiction before settling the procedure. Temporary access to carry out works also needs separate consideration; it should not be assumed that a permanent easement application is the appropriate first step.

## Preparing for advice

It helps to have the following to hand:

- current title searches, deposited or strata plans and existing easement instruments;
- the proposed easement plan and draft terms, if available;
- development consents, conditions and relevant design or engineering reports;
- correspondence, offers and any valuation material; and
- any court documents or dates already notified.

A first instruction can be a defined review of the proposal, evidence gaps and available options, with scope and fees agreed before work begins. Keep confidential documents to hand until we confirm that we can act.

## Legislation and related reading

- [_Conveyancing Act 1919_ (NSW) s 88K](https://legislation.nsw.gov.au/view/html/inforce/current/act-1919-006#sec.88K) .
- [_Land and Environment Court Act 1979_ (NSW) s 40](https://legislation.nsw.gov.au/view/html/inforce/current/act-1979-204#sec.40) .
- [Land access and easements](https://stonepillar.com.au/services/land-access-easements/) .
- [Easement rights and disputes](https://stonepillar.com.au/issues/easement-disputes/) .
- [Temporary access to neighbouring land](https://stonepillar.com.au/issues/neighbouring-land-access/) .

This page is general information only and is not legal advice. It may not be current, and how the law applies depends on the specific facts. For advice on your situation, contact Stone & Pillar Legal.

Where to start

## Discuss a proposed easement

Tell us whether you are seeking an easement or responding to a request, the properties involved and the decision you need to make. We can discuss whether the firm can assist and what a scoped first step would involve.

Have the proposed plan, correspondence and any notified court date to hand.

[Request a call back](https://stonepillar.com.au/contact/?matter=property&service=land-access-easements#enquiry)

[Speak with a lawyer](https://stonepillar.com.au/contact/?matter=property&service=land-access-easements#schedule)

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

---

The information and tools on this website are general information only and are not legal advice. Please provide only a brief outline for an initial enquiry, and keep confidential or privileged documents to hand until we tell you how to provide them. Tell us any date stated in your documents. Do not assume that an enquiry or booking protects a deadline. Ask us to confirm any work we agree to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice without waiting for our reply. See the full [Disclaimer](https://stonepillar.com.au/disclaimer/) and [collection notice](https://stonepillar.com.au/privacy/#collection-notice) .

© 2026 Stone & Pillar Legal · New South Wales

Stone & Pillar Legal is a business name of Stone & Pillar Pty Ltd ABN 11 698 040 854.

Liability limited by a scheme approved under professional standards legislation.