NSW Project Watch

Central-West Orana Renewable Energy Zone (transmission)

Renewable Energy Zone · Central West and Orana · EnergyCo NSW

Documented stage: Construction

Profile publication reviewed . Individual source-check dates appear below. Inclusion does not establish that any particular property will be acquired or affected.

Project overview

New high-voltage transmission lines, energy hubs and switching stations are being built in the Central-West Orana Renewable Energy Zone around Dubbo and Dunedoo to connect new generation to the grid.

Construction timetable

The network operator, ACEREZ, started construction in June 2025. EnergyCo expects energisation from 2028.

Land and easement agreements

EnergyCo reports that it has acquired the land and easement rights for the transmission project, with mutual agreement reached in 97 per cent of acquisition cases.

What this could mean for a property

Renewable Energy Zone transmission is generally delivered through easements and land-access arrangements over rural land. EnergyCo reports that the land and easement rights for this project have been acquired, 97 per cent of them by agreement, so for landholders the issues now are construction access, leases and temporary occupation, the conditions attached to the easements, and compensation. Whether you host infrastructure or adjoin it, those terms are worth understanding while construction continues.

Key things to watch

  • Construction access, compounds and working conditions on or near your land
  • The easement terms and conditions, if your land carries an easement
  • Compensation and any landholder payment schemes
  • Biosecurity, farming and severance effects

Possible land impacts

  • Transmission easements over rural and agricultural land
  • Survey, investigation and construction access
  • Construction compounds, leases and temporary occupation
  • Farming, biosecurity, severance and land-use effects

Possible impact types

  • Easement
  • Survey / investigation access
  • Construction lease
  • Temporary occupation
  • Access change
  • Business disturbance
  • Severance / retained land
  • Planning / corridor constraint

Documents worth gathering

  • Any easement, lease or land-access agreement, and any acquisition notice
  • Your title search and deposited plan
  • Farm and business records, if relevant
  • Correspondence and maps from the project

Location and relevant interests

Council areas: Dubbo Regional, Mid-Western Regional, Warrumbungle, Upper Hunter.

Often relevant to: Rural and agricultural landholders; Owners hosting or adjoining the transmission corridor; Lessees and farm businesses.

Official sources

Project record checked

Project information is indicative. It does not establish that a particular property is affected.

Find this project on the Project Watch hub

Where to start

Discuss your project or land concern

Tell us what has happened and what decision you need to make. The preliminary call is to discuss whether Stone & Pillar can assist and the next step. If we can assist, scope and fees are agreed before substantive legal work begins.

Request a call back

Speak with a lawyer

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

Speak with a lawyer Call