Project EnergyConnect
Transmission and energy · Riverina and Southern NSW · Transgrid
Documented stage: Construction
Profile publication reviewed . Individual source-check dates appear below. Inclusion does not establish that any particular property will be acquired or affected.
Project overview
EnergyConnect is an electricity interconnector of about 900 kilometres linking the NSW, South Australian and Victorian grids. Transgrid reports that construction and initial energisation are complete, with commissioning and testing continuing.
The NSW route
The interconnector includes 330 kV and 500 kV transmission lines. In NSW it runs from the South Australian border to Buronga, then to a new substation at Dinawan near Bundure, and on to Wagga Wagga.
Rehabilitation and commissioning
Transgrid reports that rehabilitation of the project corridor, commissioning and testing are in progress. Integration into the National Electricity Market is expected by the end of 2026.
What this could mean for a property
The line is built, but the property questions it raised can outlast construction. EnergyConnect was delivered through easements over private land, and Transgrid states that compensation is paid under the Land Acquisition (Just Terms Compensation) Act 1991. Transgrid also states that the NSW Government's Strategic Benefit Payments, a set rate per kilometre of line hosted paid annually over 20 years, apply to landowners hosting EnergyConnect, in addition to that compensation. Owners whose compensation is not yet settled, or who are unsure what they are entitled to, may want to check where their claim stands.
Key things to watch
- Whether your compensation claim has been made, determined or settled
- Strategic Benefit Payments and how they are paid
- The easement terms, including access and land-use restrictions
- Rehabilitation of the corridor, including land and fences, while it is under way
Possible land impacts
- Transmission easements over private and rural land
- Restrictions on land use, building and farming within the easement
- Continuing access for operation and maintenance
Possible impact types
Documents worth gathering
- The easement instrument and any agreement you signed
- Your title search and deposited plan
- Correspondence about compensation and Strategic Benefit Payments
- Farm and business records, if relevant
Location and relevant interests
Council areas: Wentworth, Murrumbidgee, Wagga Wagga.
Often relevant to: Rural and agricultural landholders hosting the easement; Owners adjoining the line; Lessees and farm businesses.
Official sources
- Transgrid, EnergyConnect
Source checked .
- Transgrid, EnergyConnect: landowner and community engagement
Source checked .
Project record checked
Project information is indicative. It does not establish that a particular property is affected.
Where to start
Discuss your project or land concern
Tell us what has happened and what decision you need to make. The preliminary call is to discuss whether Stone & Pillar can assist and the next step. If we can assist, scope and fees are agreed before substantive legal work begins.
30 minutes · Phone or Teams · No charge
The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.