NSW Project Watch

VNI West (NSW section) and South West REZ network upgrade

Transmission and energy · Riverina and Southern NSW · Transgrid

Documented stage: Planning and assessment

Profile publication reviewed . Individual source-check dates appear below. Inclusion does not establish that any particular property will be acquired or affected.

Project overview

A proposed 500 kV double-circuit transmission line linking the NSW and Victorian electricity grids. In NSW it would run for about 240 kilometres between the Victorian border near Murrabit and the Dinawan substation north of Jerilderie. Transgrid's project page, read on 20 November 2026, says the Department of Planning, Housing and Infrastructure is reviewing the application and that Transgrid anticipates a decision on project approval in late 2026.

Route and scope

Transgrid's environmental impact statement summary describes new double-circuit 500 kV transmission lines from the NSW and Victorian border to the future Dinawan substation, a distance of around 240 kilometres. It also describes the demolition and rebuild of about nine kilometres of an existing 330 kV line near Wagga Wagga, and an expansion of the future Dinawan substation.

Planning status

The environmental impact statement was on public exhibition from 1 to 29 August 2025. Transgrid's fact sheet on the Submissions Report and Amendment Report says both have been submitted to the Department of Planning, Housing and Infrastructure for review before a determination is made. It says the amendments include delivering the project in two stages and additional equipment at the future Dinawan substation. On 20 November 2026 the NSW Planning Portal showed the application (SSI-72887208) at the More Information Required stage. Transgrid's project page, read on the same day, says it anticipates a decision on project approval in late 2026.

South West REZ works

On 10 July 2026 EnergyCo announced a Project Development Deed with Transgrid for the South West Renewable Energy Zone. EnergyCo says the agreement accelerates works that include upgrading Dinawan substation to operate at 500 kV, a new switchyard at Dinawan, and converting the existing Dinawan to Wagga Wagga powerlines from 330 kV to 500 kV.

Land and easements

Transgrid's land use and agriculture fact sheet says land and easements will be acquired in consultation with landholders and in line with legislation, with compensation under the Land Acquisition (Just Terms Compensation) Act 1991 and additional Strategic Benefit Payments for landowners hosting infrastructure. It says individual Property Management Plans will be developed in consultation with landholders. The environmental impact statement summary says the easement for the new 500 kV lines would typically be 70 metres wide, and up to around 110 metres at some locations.

What this could mean for a property

Transgrid's August 2025 fact sheet says land and easements will be acquired in consultation with landholders and in line with legislation, with compensation under the Land Acquisition (Just Terms Compensation) Act 1991 and additional Strategic Benefit Payments for landowners hosting infrastructure. Its environmental impact statement summary, which predates the Amendment Report, says the new 500 kV lines would need an easement typically 70 metres wide, and up to around 110 metres at some locations, that most of the land in the project footprint is used for agriculture, and that construction would need temporary leases or licences of land. Being near the proposed route does not mean a property will be affected, but easement terms, property management plans and access arrangements are worth understanding before anything is signed.

Key things to watch

  • The State and Commonwealth approval decisions, which Transgrid anticipates in late 2026, and any conditions
  • Easement offers, property management plans and how long negotiation runs before any compulsory acquisition step
  • Works at Dinawan under the South West REZ Project Development Deed
  • Timing of the line between Dinawan and the Victorian border

Possible land impacts

  • Transmission line and access easements, typically 70 metres wide for the new 500 kV line
  • Acquisition of land for permanent works, where required
  • Temporary leases or licences of land for construction and ancillary facilities
  • Ongoing limits within the easement, including on aerial agriculture and some farm operations

Possible impact types

  • Easement
  • Partial acquisition
  • Construction lease
  • Severance / retained land
  • Noise / vibration / amenity

Documents worth gathering

  • The EIS, Amendment Report and Submissions Report on the NSW Planning Portal (SSI-72887208)
  • Any easement offer, option or property management plan from Transgrid
  • Your title search and deposited plan
  • Farm maps and records of airstrips, irrigation and aerial operations

Location and relevant interests

Council areas: Murray River, Edward River, Murrumbidgee, Wagga Wagga.

Often relevant to: Landholders along the proposed route between the Victorian border near Murrabit and Dinawan; Landholders near the Dinawan substation and the line works near Wagga Wagga; Farm businesses, irrigators and aerial agriculture operators.

Official sources

Project record checked

Project information is indicative. It does not establish that a particular property is affected.

Find this project on the Project Watch hub

Where to start

Discuss your project or land concern

Tell us what has happened and what decision you need to make. The preliminary call is to discuss whether Stone & Pillar can assist and the next step. If we can assist, scope and fees are agreed before substantive legal work begins.

Request a call back

Speak with a lawyer

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake.

Speak with a lawyer Call